Hi,
We have SAP Analysis for Office 1.4 and the BPC EPM 10.0 running in concurrently on Client machines.
We were planning to upgrade AO to 2.2 and take advantage of both the Analysis & EPM Plugins. In the process the old EPM 10.0 would be uninstalled. '
However, during the course of testing the new EPM Plugin within AO 2.2, we found there are a lot of changes (especially in the VBA Macros) needed many of which are not Backward Compatible with the Old EPM 10.0.
In the interest of time, we are considering the option to upgrade only the Analysis Plugin for from 1.4 to 2.2 and keep the EPM Plugin as it is, i.e. on EPM 10.0.
I have not seen any documentation/Note describing this scenario and if this will work? Does anyone have know how if this work and what are the considerations to take.
Best
Zubin Kurian